Estimating, cost and earned value

“How long will it take?” is the hardest question in projects. Three common ways to estimate:

AnalogousFrom a similar past project: “the last app took 3 months”. Quick and rough.
ParametricRate × quantity: 20 screens × 3 days a screen = 60 days.
Three-point (PERT)Ask for the optimistic (O), most likely (M) and pessimistic (P) cases and take a weighted average.
PERT = (O + 4×M + P) ÷ 6

The budget = the cost of all work packages + a contingency reserve for expected problems. Once the project is running, how do you know you're on track? “We've spent half the budget” isn't enough: half on how much work? That's where earned value management (EVM) comes in:

PVPlanned value: the value of work that should be done by now.
EVEarned value: the value of work actually done (% complete × budget).
ACActual cost: what we've actually spent.
CPI = EV ÷ ACBelow 1 = over budget.
SPI = EV ÷ PVBelow 1 = behind schedule.

Total budget: 400k SAR

PV200
EV160
AC200
CPI0.80
SPI0.80
Forecast final cost500

Behind schedule and over budget: this needs a management decision (red).